How to use our feedback map

Register

To give us your feedback on the project, you will need to register. Please provide us with your name, email, and postcode and tell us if you are responding on behalf of an organisation or as an individual.

Registration page

You will be sent an email to confirm your identity. Please click the link in the email to confirm. If you are not automatically logged in please click on login.

Click here to view our GDPR Policy on how we manage data for this project.

Login

Visit login and enter your email and password.

Login page

Add your feedback

You can zoom and move the map around to the location you wish to leave feedback.

Leave feedback

Click on the map and a panel will pop out to allow you to leave a comment at that point:

Feedback panel open

Type your comment into the text box. If you wish to provide lengthy feedback (greater than 1000 characters), please write your comment in a document i.e. Word and upload it as an attachment at the bottom of the page.

Click on ‘Add my comment’ to add your feedback to the map. Your pointer will appear on the map. This is important as your comment will not be registered unless you click here to send it to us.

Please note: You are unable to edit a comment once it has been submitted. If you wish to leave additional feedback please add a further comment.

Features

Route corridors and plot your location

You are able to turn the project’s permanent and temporary layers on and off. The permanent layer includes the indicative pipeline centre line, Hydrogen Above Ground Installations (HAGIs) and Block Valve Installations (BVIs). The temporary layer includes areas we’ll temporarily need for construction access and storage. You can also enter your postcode to see how close you are to the area (please note that locations further than 2km from the consultation area are now viewable).

Map controller

List view

You can view a list of all of your feedback either on the map or using the ‘list view’:

List view

Our proposals

At our second, statutory consultation we presented preliminary order limits, an indicative pipeline centre line, pipeline route options and potential Hydrogen Above Ground Installation (HAGI) and Block Valve Installation (BVI) locations.

We are now analysing feedback, carrying out lots more technical, engineering and environmental work, as well as continuing to engage key stakeholders – all with the aim of developing a final design which we’ll submit to the Planning Inspectorate for consideration.

View how our proposals have developed

Interactive map (under review)

This map shows an overview of the proposals we presented at our second, statutory consultation – the area where our pipeline will be routed and temporary construction areas located, as well as potential Hydrogen Above Ground Installation (HAGI) and Block Valve Installation (BVI) locations.

Please note that this map shows the Northwich Spur, which has now been removed from the Development Consent Order. You can read an update about the removal of the Northwich spur here.

See map

Have your say

We want to hear your views. There are plenty of ways for you to submit your feedback on our proposals for Cadent's HyNet North West Hydrogen Pipeline.

Leave feedback

Please note, the deadline for submitting feedback is at 23:59 on 10 November 2022.