Programme update

Programme update

Activity Start End
DCO application preparation
Application Ecology surveys (pre construction surveys will also be completed) January 22 March 25
Targeted consultation Late January 25 Late February 25
Adequacy of consultation milestone application January 25
Draft DCO application documents April 24 April 25
Final ES chapters October 24 April 25
DCO application submitted May 25
DCO decision received Autumn 26
PINS engagement
Document review March 25 April 25
Topic based meeting #1 January 25
PINS meeting #2 February 25
PINS meeting #3 March 25
PINS meeting #4 April 25
HSE
HSE review of Safety Case July 26 December 28
Detailed Design and Construction
Detailed design 2026 2027
Land liaison for construction works 2026 2029
Site mobilisation 2027 2029
Main construction 2027 2029
Operation
Commissioning complete and operation commences 2030