Programme update
Programme update
Activity | Start | End |
---|---|---|
DCO application preparation | ||
Application Ecology surveys (pre construction surveys will also be completed) | January 22 | March 25 |
Targeted consultation | Late January 25 | Late February 25 |
Adequacy of consultation milestone application | January 25 | |
Draft DCO application documents | April 24 | April 25 |
Final ES chapters | October 24 | April 25 |
DCO application submitted | May 25 | |
DCO decision received | Autumn 26 | |
PINS engagement | ||
Document review | March 25 | April 25 |
Topic based meeting #1 | January 25 | |
PINS meeting #2 | February 25 | |
PINS meeting #3 | March 25 | |
PINS meeting #4 | April 25 | |
HSE | ||
HSE review of Safety Case | July 26 | December 28 |
Detailed Design and Construction | ||
Detailed design | 2026 | 2027 |
Land liaison for construction works | 2026 | 2029 |
Site mobilisation | 2027 | 2029 |
Main construction | 2027 | 2029 |
Operation | ||
Commissioning complete and operation commences | 2030 |