Update - 09 October 2024

Updated project programme

Please see below for an updated project programme as of 9 October 2024.

Activity Start End
DCO application preparation
Ecology surveys January 22 March 25
Stage Three Statutory Consultation 14th October 24 19th November 24
Consultation analysis and response preparation November 24 December 24
Consultation report development December 24 December 24
Adequacy of consultation milestone application December 24
ES Design Freeze December 24
Draft DCO application documents April 24 March 25
Final ES chapters October 24 March 25
DCO application submitted March 25
DCO decision received July 26
PINS engagement
Document review December 24 February 25
PINS meeting #1 December 24
Topic based meeting #1 December 24
PINS meeting #2 January 25
Topic based meeting #2 January 25
PINS meeting #3 February 25
Topic based meeting #3 February 25
PINS meeting #4 March 25
Topic based meeting #4 March 25
HSE
HSE review of Final Safety Case June 26 December 27
Detailed Design and Construction
Detailed design July 25 February 27
Land liaison for construction works January 26 February 27
Site mobilisation February 27 May 27
Main construction April 27 December 29
Operation
Commissioning complete and operation commences Spring 2030
Back to news

Register for updates

Please register your contact details with us if you would like to be kept informed about our project.

Register here