Update - 09 October 2024
Updated project programme
Please see below for an updated project programme as of 9 October 2024.
Activity | Start | End |
---|---|---|
DCO application preparation | ||
Ecology surveys | January 22 | March 25 |
Stage Three Statutory Consultation | 14th October 24 | 19th November 24 |
Consultation analysis and response preparation | November 24 | December 24 |
Consultation report development | December 24 | December 24 |
Adequacy of consultation milestone application | December 24 | |
ES Design Freeze | December 24 | |
Draft DCO application documents | April 24 | March 25 |
Final ES chapters | October 24 | March 25 |
DCO application submitted | March 25 | |
DCO decision received | July 26 | |
PINS engagement | ||
Document review | December 24 | February 25 |
PINS meeting #1 | December 24 | |
Topic based meeting #1 | December 24 | |
PINS meeting #2 | January 25 | |
Topic based meeting #2 | January 25 | |
PINS meeting #3 | February 25 | |
Topic based meeting #3 | February 25 | |
PINS meeting #4 | March 25 | |
Topic based meeting #4 | March 25 | |
HSE | ||
HSE review of Final Safety Case | June 26 | December 27 |
Detailed Design and Construction | ||
Detailed design | July 25 | February 27 |
Land liaison for construction works | January 26 | February 27 |
Site mobilisation | February 27 | May 27 |
Main construction | April 27 | December 29 |
Operation | ||
Commissioning complete and operation commences | Spring 2030 |